Grong Grong HV & Street Lighting

  • Location: Grong Grong, NSW
  • Customer: Georgiou Group
  • Gallery:
    • Image:
    • Image:
  • Work Heading: Scope of work
  • Work Heading (Custom): Testing Custom
  • List:
    • Item: Supply and install category V lighting located at two primary intersections of the Newell HWY
    • Item: Extend high voltage network to intersection
    • Item: Installation of new 16kva high voltage pole mount substation at each intersection
  • Image:

Roads and Maritime Services has moved the Newell Highway west of Grong Grong to improve freight efficiency and road safety. The NSW Government has provided $17 million for the project, which will support the long-term future and viability of the local area. Georgiou Group Pty Ltd was selected as the successful contractor for the project and started work on the site of the new alignment in December 2016. The project was completed on schedule in February 2018.

  • Hits: 16

Rural Fire Service (RFS) - Southwest Slopes Zone Fire Control Centre

  • Location: Harden, NSW
  • Customer: NSW Public Works
  • Gallery:
    • Image:
    • Image:
  • Work Heading: Scope of work
  • Work Heading (Custom): Testing Custom
  • List:
    • Item: Installation of a 315Kva high voltage pole mount substation
    • Item: Upgrade 1.8km of the existing Essential Energy Network from single phase to three phase
    • Item: Installation 470m of high voltage overhead and underground cable to site
  • Image:

The Centre is in the RFS Southwest Slopes Zone and construction began in September of 2019. The brand-new Centre will feature state of the art facilities which will provide better support to RFS members during incidents as well as enhanced training capabilities.

  • Hits: 16

Gundagai Sewage Treatment Plant

  • Location: Gundagai, NSW
  • Customer: Cootamundra-Gundagai Regional Council
  • Gallery:
    • Image:
    • Image:
    • Image:
  • Work Heading: Scope of work
  • Work Heading (Custom): Testing Custom
  • List:
    • Item: Relocate and remove overhead high voltage powerline from the treatment plant site
    • Item: Install 400m of underground high voltage cable
    • Item: Install 500KVA Pad mount Substation on culvert footing
  • Image:

The new plant will meet projected increases over the next 30 years. The new biological treatment is based on the Intermittently Decanted Extended Aeration (IDEA) treatment process, to which micro-organisms contained within the sewage treatment process, aid to break down organic matters. Management of the treated effluent continues via the existing effluent reuse system with remaining excess (if any) to discharge into the Murrumbidgee River. Due to the out-date plant Inland Power Solutions were able to install 500Kva to power the new plant.

  • Hits: 16

Brunslea Park

  • Gallery:
    • Image:
    • Image:
    • Image:
    • Image:
  • Work Heading: Construction included
  • Work Heading (Custom): Testing Custom
  • List:
    • Item: Low Voltage Underground reticulation servicing 31 lots
    • Item: Streetlighting to meet Wagga Wagga City Councils P4 Lighting Category
    • Item: High Voltage Overhead Powerline and Pole Mount Transformer removal prior to the new reticulation connection
    • Item: Maintaining power to an existing dwelling with no disruptions throughout construction
  • Image:

Brunslea Park Stage 13A, was a 31-lot residential subdivision located in Forest Hill, Wagga Wagga. This subdivision had both Low and High Voltage aspects and was constructed by Inland Power Solutions team in January 2017.

  • Hits: 26

Jindera Industrial Estate

  • Gallery:
    • Image:
    • Image:
    • Image:
    • Image:
    • Image:
  • Work Heading: Subdivision required
  • Work Heading (Custom): Testing Custom
  • List:
    • Item: Thirteen New Power Poles bearing High Voltage and Low Voltage Overhead Conductor
    • Item: Two 315kva Pole Mount Transformers
    • Item: Underground Low Voltage was installed to supply two Industrial Pillars within the cul-de-sac
  • Image:

Greater Hume Shire new 15 lot industrial estate on the southern boundary of the existing Jindera Industrial Estate, right on the door step of Albury/Wodonga.

Inland Power Solutions have been engaged by Greater Hume Shire to Build the Overhead / Underground Electrical Reticulation for the 15 Lot Industrial Subdivision.

  • Hits: 16